Here we are, only a few short weeks until our Grand Opening. Stay tuned for the actual date. Much progress has been made since the last set of photos. Drywall is in and so is the heating/air conditioning, electrical, phones, network cabling, intercoms, plumbing and ceiling grids. This week the WatchMeGrow internet camera system will be installed (a free service to you!). Paint is starting, cabinets will be set as will be the ceiling tiles, door frames, interior lighting, and exterior doors and windows. Exterior illuminated signage is expected to be hung this week, too. Playground construction should start this week. In the next couple of weeks the flooring will be installed. This is one of the final installations, but also takes the most time. The Certificate of Occupancy should be in hand in a couple of weeks, which kicks off the final childcare inspections, including DCF, the health department and fire safety.